Case study
iScala 3.4 Migration at Merck: A Global ERP Upgrade Without Disrupting Operations
4 minutes
iScala 3.4 Migration at Merck: a global ERP upgrade
Migrating an ERP system used across many countries takes far more than installing a new version. For Merck KGaA, the project covered 19 subsidiaries, around 120 system modifications and more than 100 interfaces connecting iScala with other solutions.
The goal of the project led by MINDBOX was to migrate from iScala 3.0 to version 3.4 with the least possible impact on users’ daily work and the continuity of business processes. The work was planned for 14 months and divided into successive migration waves.
Client: Merck KGaA
System: Epicor iScala ERP
Scope: migration from iScala 3.0 to 3.4
Scale: 19 subsidiaries, around 450 concurrent remote users, more than 100 interfaces
Planned project duration: 14 months
iScala in the global ENVIRONMENT of Merck
Merck had been using iScala for more than a decade. The system served as the ERP solution for the organization’s smaller units (Tier II) and supported standardized business processes. Around 450 remote users worked in the environment at the same time. Support was provided by the Global Scala team operating from Darmstadt and Singapore.
Over the years, the system had been extensively tailored to the organization’s needs. The environment included:
- around 120 system modifications,
- hundreds of reports, documents and OLAP cubes,
- more than 100 interfaces to internal systems and business partners’ solutions.
Moving these elements to the new version of iScala and testing them thoroughly was a significant part of the scope of work.
The challenge: switching platforms WITHOUT DISRUPTING the business
The main goal was to move to iScala 3.4 with minimal disruption to Merck’s operations. The migration concerned an environment used in many countries and closely connected with the rest of the IT architecture. The project also had to account for the requirements of the pharmaceutical industry, including legal constraints and data security.
The scale of the challenge was increased by users spread across 18 countries, a project team of more than 20 people working in 10 countries, and restrictions related to the COVID-19 pandemic. Most of the work was carried out remotely. With so many modifications and integrations, precise planning, testing and a phased rollout were essential.
Why did Merck choose MINDBOX?
MINDBOX and Merck had worked together before, so the team already knew the client’s environment and the specifics of iScala. When selecting a partner, Merck considered the proposed schedule, cost and delivery approach. MINDBOX’s experience with Epicor systems and complex international IT projects also played a role.
MINDBOX led the migration project with the support of a dedicated team set up by Merck. The scope included the technical migration of components and the coordination of successive project stages.
Solution: phased migration from iScala 3.0 to 3.4
The project was planned for 14 months. The migration was split into a pilot and successive waves covering groups of countries, so that changes could be tested before the next stage went live.
- Migration of technical components. Preparing the system, modifications, reports, documents, OLAP cubes and interfaces for transfer to the new version.
- Test migration and pilot. A one-month internal testing period was planned, with Sweden selected as the first pilot country.
- Rollout to successive country groups. After the pilot, the upgrade was scheduled in three waves, each covering a group of four to eight countries.
- Testing and post-go-live support. Each group was to go through a test migration, user acceptance testing (UAT), final migration and post-go-live support.
This plan made it possible to limit the scale of simultaneous change and to apply lessons learned from previous waves.
Expected BENEFITS for the business
Upgrading iScala was intended to reduce the risks of continuing to run on an older platform and to prepare the environment for the years ahead. The project’s objectives included:
- maintaining system continuity and stability for the next five years,
- reducing legal risk and the related costs,
- moving to a more up-to-date technology platform,
- greater flexibility thanks to the features available in iScala 3.4.
After the migration, users were not expected to notice any significant change in their daily work. The new version was meant to run faster, more efficiently and more securely.
Summary: modernizing ERP while maintaining business continuity
The Merck project shows how the migration of a heavily modified ERP system was planned in an international organization. The number of countries, integrations and custom elements required extensive testing and splitting the work into smaller waves. The overriding goal remained modernizing the environment with the least possible impact on the company’s day-to-day operations.
Planning an ERP migration or development? MINDBOX helps organizations migrate, develop and maintain ERP environments, including Epicor iScala and Epicor Kinetic. Explore MINDBOX ERP solutions.
Interested in WORKING WITH US?
Book a meeting
Tell us about your project
Contact us